Thursday, 28 June 2012

June 28 More building paper and doors


 Completion of building paper application, and patio doors and temporary front door installed.


Wednesday, 27 June 2012

June 27 Building paper

 Building paper being applied and mock-up of window framing. The white frames will be painted black.


 Bulkhead added to basement kitchen (above), and hallway (bottom).

 Utility room under the stairs in the basement.
 Basement doorway
 Security wiring.
 Heat recovery ventilation (HRV) pipes


June 25 LWH Roof Tiling

 LWH roof is tiled.

 Venting and bathroom fan.

Sunday, 24 June 2012

June 23 LWH progresses


 Skylight


 Garage
Kitchen window to the right. 
Bathroom and bedroom windows
 
 Bedroom and bathroom
 Bedroom windows
Bathroom




 Electrical
 3 lights for the kitchen and sprinkler on bottom right.

Thursday, 21 June 2012

June 21 Some Painting

 More framing of the LWH and the painters have started painting the trim.


Boxes for light switches.

Wednesday, 20 June 2012

Tuesday, 19 June 2012

June 19 LWH takes shape

 LWH framing started today.



 The 3 windows facing the back of the house are too high - have to be lowered by 7".
 Kitchen is at the front left, bedroom back left, bathroom is middle back, garage to the right.

 The orange pipes are for the sprinklers.


 Some insulation in basement suite bathroom (above), living room fireplace area (below).

 Upstairs bathroom insulation.